Soul Lifestyle Medellin - Construction Period March 2015 - December 2016

Soul Lifestyle Medellin - Construction Period March 2015 - November 2016

The Soul Lifestyle project was conceived with a simple goal in mind: to be the #1 luxury rental building in Medellin for both investors and our eventual renters.

Top features

We designed Soul from the ground up to offer what will be the longest list of high quality amenities you will find anywhere in Medellin:

80 apartments with the most modern kitchen and bathroom finishings, air conditioned apartment and balconies in every unit
Rooftop Sky Club with lounge, heated pool, jacuzzi, turkish steam bath, BBQ zone, full size gym, meeting rooms and chef's kitchen
The most technologically advanced features like solar power hot water and fibre optic internet to all suites.

Investors

Sales for the Soul project have now been completed but as a premier investment property in Medellin with rental track record since 2017, select resale opportunities are often available. Please contact sales@casacol.co for more information about resale units in Soul or visit our sales page at listings.casacol.co.

Location

Our location is unbeatable. We are located on Carrera 34 and Calle 3 Sur, just steps or a short taxi ride from the very best of El Poblado. Easy access to Las Palmas via Los Balsos ensures quick and easy airport arrivals and departures.

Rentals in Soul

Rentals in Soul today can be found at our dedicated Soul Medellin rentals page or view Ximena's profile on Airbnb with 1000s of wonderful reviews and comments. We look forward to hosting you in Soul!

Monthly Construction Updates

Additional photos contained within this Dropbox link.

March 2015

Site preparation, hiring of more than 60 contractors.

April 2015

Initial excavation to a depth of 18 meters for construction of parking levels.

May 2015

Construction of 40 perimeter columns to be filled with concrete and steel to form retaining wall.

June 2015

Finishing of the perimeter reinforcements prior to further excavation.

July 2015

Completion of perimeter reinforcements.

August 2015

Excavation and perimeter complete. Footings and foundational column construction begins.

September 2015

Foundational column construction in what will be 2nd floor of parking garage.

October 2015

Continued work on second floor of parking garage.

November 2015

Construction of 2 level parking area now complete, lobby level construction to begin.

December 2015

Finishing of lobby level and start of second floor construction.

January 2016

Third floor of Soul project takes form.

February 2016

Fourth and fifth floor construction progress.

March 2016

7th floor construction and installation of brick facade.

April 2016

Construction continues on 9th floor. Brick façade reaches fifth floor.

May 2016

Soul has now reached structural completion. Brick facade at 8th floor.

June 2016

Attention turns to interiors. Project at peak 125 daily workers on site.

July 2016

Finishing of all exterior glass and balconies.

August 2016

Prototyping of furnishing package begins.

September 2016

Top floor pool and common area progress, furnishing of beta suite on 2nd floor for next month.

October 2016

Completely finished unit on 2nd floor, furnishing of model suite to commence.

November 2016

Testing of solar hot water system, will supply 90% of hot water to Soul.

December 2016

Interior furnishing process has commenced, first apartments go operation on January 2.

January 2017

Commencement of daily rental operations.

April 2017

Soul as seen from aerial drone.